The concrete continues to flow!

The cold and snow isn't slowing down construction progress at our main branch on Parker Street! Foundation and retaining wall work contiunes this month with the addition of many of the basement walls and the elevator pit already complete. We have some large equipment on site such as a crane and pump truck, which have been exciting to watch.

crane.jpg

east-retaining-wall.jpg

basment-walls-pump-truck.jpg

Footing, basement and retaining wall concrete work will continue through January. Check back soon for more updates on our continued progress.